The Cabinet has approved awarding a Rs. 1.73 billion contract to build a 10-storey block for the University of Kelaniya’s Faculty of Commerce and Management Studies, restarting a project abandoned during the economic crisis.

The contract goes to M/s Sathuta Builders (Pvt) Ltd, EconomyNext reported at 3.29 p.m. on Tuesday. The approved sum excludes Value Added Tax, a qualification both filings carry — so the figure is a floor, not the final cost to the state.

The proposal was submitted by the Prime Minister in her capacity as Minister of Education, Higher Education and Vocational Education, Hiru News reported. Hiru’s filing does not name the contractor, describing the winner only as a private institution.

A tender nearly two years in the running

The procurement traces back to 3 February 2025, when Cabinet approved resuming the stalled project through national competitive bidding. That call drew ten bids.

Hiru’s account is more specific than EconomyNext’s on how the winner was chosen: the bids were evaluated and the award made on recommendations from both the Higher-Level Procurement Committee and the Procurement Appeals Board. EconomyNext compresses this to “the procurement committees.”

“Following the evaluation of the bids, the contract is awarded to the lowest substantially responsive bidder based on recommendations from the procurement committees,” Cabinet spokesperson Nalinda Jayatissa said.

Context

Kelaniya’s physical plant has been a live issue on campus. Students held a torch-lit night protest on 3 November demanding hostel places for every applicant and the construction of new hostels — a separate class of building from the faculty block approved here, and one no Cabinet decision has yet addressed.

A figure to keep apart: the Cabinet also approved a Rs. 1,725.7 million Indian grant for 100 Suwa Seriya ambulances at the same Tuesday briefing. Both decisions round to Rs. 1.73 billion and were announced within hours of each other. They are unrelated.

Not reported

Neither filing gives a construction timetable, a completion date, or the funding source for the contract — whether it is Treasury-funded, loan-financed or drawn from the university’s own capital vote. Neither says how much was already spent before the project stopped, how far the structure had progressed, or what the original pre-crisis contract value was, which would show how much the delay has cost. Neither states the building’s floor area or how many additional students the faculty will be able to take.