The Cabinet of Ministers has allocated Rs 502.16 billion for expressway, highway and rural road development, clearing 23 construction contract packages across two major expressway projects.

The decision was taken at the Cabinet meeting held on Monday (16), Hiru News reported, citing the Government Information Department.

Where the money goes

ItemAllocation
Ruwanpura Expressway, phase 1 (Kahathuduwa–Ingiriya), 11 packagesRs 251.37 billion
Central Expressway section 4, phase 1 (Kurunegala–Galewela), 12 packagesRs 243.44 billion
National highway widening and highway infrastructure rehabilitationRs 5.83 billion
Rural road rehabilitation and improvementRs 1.52 billion
TotalRs 502.16 billion

The four published figures sum exactly to the stated total.

Ruwanpura Expressway

The first phase of the Ruwanpura Expressway covers a 22.18-kilometre section from Kahathuduwa (km 1+820) to Ingiriya (km 24+000), including a system interchange, the Daily Mirror reported.

Construction of that phase was first approved by Cabinet on 27 July 2026. Bids were then invited under the National Competitive Procurement System and split into 11 separate contract packages. Cabinet approved the awards on proposals submitted by the Minister of Transport, Highways and Urban Development, acting on the recommendations of the High Level Procurement Committee.

Central Expressway, Kurunegala–Galewela

The 12 remaining packages cover a 38.5-kilometre stretch from Kurunegala (km 78+000) to Galewela (km 116+500), the first phase of the Central Expressway’s fourth section running from Kurunegala to Dambulla, the Daily Mirror reported separately.

That phase was approved by Cabinet on 30 June 2026. The contracts were awarded to the lowest responsive bidders, again on the High Level Procurement Committee’s recommendations.

Approved amid criticism over unspent capital

Update, 17 November: EconomyNext reported the same approvals on Tuesday evening, attributing them to Cabinet Spokesman Nalinda Jayatissa and framing them against “growing criticism over unspent capital spending allocated in [the] 2026 budget,” in its account of the decision.

Citing Treasury officials, EconomyNext put spending at less than 25 per cent of the Rs 1,380 billion allocated for capital expenditure in the first nine months of this year. The government acknowledged the delay and blamed lingering approval and procurement processes, saying a new advanced approval and procurement process has been planned for 2027, for which it has allocated a record Rs 2,000 billion in capital expenditure.

That context cuts directly against the approvals above: Cabinet is awarding Rs 502.16 billion in construction packages at the same time as the Treasury is reporting that it cannot disburse the capital budget it already has.

A figure to treat with care

EconomyNext’s “less than 25 per cent” does not match this desk’s own earlier reporting on the identical measure. On 12 October this desk reported that the government had spent under 30 per cent of its 2026 capital budget through September — Rs 385 billion of Rs 1,380 billion, or 27.9 per cent.

The denominator is identical (Rs 1,380 billion) and the period is the same nine months, so the two figures describe the same metric and genuinely diverge. That earlier article already noted three other figures for the same budget in circulation. Neither filing is reconciled against the other, and this desk does not resolve it here: readers should treat the capital-execution rate as contested within a band of roughly 25–28 per cent rather than as a settled number.

Opposition criticism

EconomyNext also reported that opposition legislator Harsha de Silva told parliament on Monday that the government has been unable to spend money on projects, citing grassroots anecdotal evidence involving a smart classroom.

“The treasury has been collecting money through tax after tax, but the government has failed to spend it and create jobs,” de Silva said.

EconomyNext gives the aggregate as “nearly Rs 500 billion” where the Sinhala and Daily Mirror filings itemise it at Rs 502.16 billion; the difference is rounding, not a discrepancy.

How this relates to Budget 2027

These figures are contract awards, not annual budget lines, and should not be read against the Budget 2027 road allocations directly. In his budget speech on 12 November, President Anura Kumara Dissanayake set out Rs 487 billion for road development in 2027, with Rs 30,000 million against the Kurunegala–Galewela expressway for that year. The Rs 243.44 billion approved this week is the total value of the construction packages for that section, spanning the life of the works rather than a single year.

Update, 18 November: minister says “zero loans”

Transport and Highways Minister Bimal Rathnayake has said the two expressways will be financed entirely from tax revenue, without borrowing, the Daily FT reported on Wednesday. In a post on X, he said the government had allocated Rs 451 billion for the Ruwanpura Expressway and the Kurunegala–Galewela section of the Central Expressway, that the projects were “100% funded by tax revenue” with “zero loans”, and that Cabinet had approved both. “People elected clean, capable leadership,” he added.

That is the first statement on financing for these awards, which none of Tuesday’s filings addressed. It is the minister’s claim, made on social media, and is not itemised in any budget document this desk has seen.

His total does not match the Cabinet figures. The two expressway allocations reported on Tuesday — Rs 251.37 billion and Rs 243.44 billion — add up to Rs 494.81 billion, which is Rs 43.81 billion more than the minister’s Rs 451 billion. Neither the post nor the Daily FT report explains the gap. It could reflect taxes, contingencies or a different scope, but nothing on record says which.

Update, 18 November: who won the Rs 7.36 billion in smaller contracts

The two smaller lines in the table above are Rs 5.83 billion for national highways and Rs 1.52 billion for rural roads. The Daily FT has now itemised them contract by contract and named the winning bidders. Its five contracts total Rs 7.36 billion, which matches those two lines.

ContractorRoad worksValueBids
Maga Engineering LtdColombo–Ratnapura–Wellawaya–Batticaloa (AA004) Road, km 38+970 to km 59+000 (about 20 km), plus the 900 m Avissawella Access Road and 100 m Avissawella Town RoadRs 4.51 billion6
Tudawe Brothers LtdKelaniya–Mudungoda Road, km 6+500 to km 29+100 (22.6 km), Gampaha DistrictRs 687.22 million3
Sanguine Engineering LtdRestoration of cyclone-damaged sections of the Peradeniya–Deltota–Rikillagaskada RoadRs 635.87 million5
RR Construction LtdKalutara District rural road rehabilitation, first contractRs 752.41 million (excl. VAT)—
RR Construction LtdKalutara District rural road rehabilitation, second contractRs 773.33 million (excl. VAT)—

The first three contracts total Rs 5,833.09 million, which is the Rs 5.83 billion highways line. They come under the National Highways Widening and Improvement Program and the program to rebuild roads damaged by Cyclone Ditwah. Each went to the lowest substantially responsive bidder on the recommendation of a High-Level Procurement Committee.

The two Kalutara contracts total Rs 1,525.74 million. Hiru’s Rs 1.52 billion is that figure cut to two decimal places rather than rounded. Cabinet Spokesman Nalinda Jayatissa said the two awards complete a five-package rural road tender that drew 17 bids under the National Competitive Procurement process. Cabinet approved the first three packages from that tender on 21 September 2026.

The Daily FT’s description of the Sanguine contract’s location contradicts itself. It says “around kilometre 38” and then “the 41st kilometre through to the 42nd kilometre”. For that reason the table gives no chainage for that contract.

Update, 18 November: who won the 23 expressway packages

The Daily FT has now published the full award list for the 23 expressway packages, which no earlier filing carried. Cabinet Spokesman Nalinda Jayatissa announced the awards at the weekly post-Cabinet media briefing. The paper adds one detail the earlier reports did not: both expressway totals include value added tax (VAT).

Nine firms won all 23 packages:

ContractorRuwanpura (Kahathuduwa–Ingiriya)Central Expressway (Kurunegala–Galewela)Total
Maga Engineering LtdRs 23.01bn, Rs 16.98bnRs 14.15bn, Rs 26.28bn, Rs 24.45bnRs 104.87bn (5)
International Construction Consortium LtdRs 34.94bnRs 16.88bn, Rs 22.51bnRs 74.33bn (3)
Access Engineering PLCRs 27.99bn, Rs 17.62bnRs 22.39bnRs 68.00bn (3)
NEM Construction LtdRs 24.30bnRs 16.15bn, Rs 24.61bnRs 65.06bn (3)
K.D.A. Weerasinghe & Co. LtdRs 33.11bnRs 27.29bnRs 60.40bn (2)
Edward and Christie LtdRs 16.15bnRs 18.39bnRs 34.54bn (2)
RR Construction LtdRs 17.96bnRs 15.90bnRs 33.86bn (2)
Tudawe Brothers LtdRs 18.48bnRs 14.44bnRs 32.92bn (2)
Senura–Sanken joint ventureRs 20.83bn—Rs 20.83bn (1)
TotalRs 251.37bn (11)Rs 243.44bn (12)Rs 494.81bn (23)

The individual awards add up exactly to both section totals reported on Tuesday. The per-contractor totals in the last column are this desk’s sums; the Daily FT lists the awards one by one.

What the list shows:

The Daily FT does not give the chainage of any package, the number of bids for each, or whether every package went to the lowest bidder. It says only that the awards followed National Competitive Procurement procedures, bid evaluations and the recommendations of the High-Level Procurement Committees.

VAT does not explain the minister’s figure

The VAT detail bears on the gap noted above between the minister’s Rs 451 billion and the Rs 494.81 billion Cabinet total. If the Rs 494.81 billion includes VAT, removing it at the current 18 per cent rate would leave about Rs 419 billion, which is below the minister’s figure. Neither the VAT-inclusive total nor a VAT-exclusive one matches Rs 451 billion, so the gap remains unexplained.

”Nearly a quarter” of the capital budget

The Daily FT also describes the awards as nearly a quarter of the Rs 2 trillion capital-expenditure allocation in the 2027 Budget. The arithmetic holds (about 24.7 per cent), but the comparison sets the full value of multi-year construction contracts against one year’s allocation. As noted above, the 2027 Budget earmarks Rs 30 billion for Kurunegala–Galewela next year.

Not reported

None of the five filings gives the names of the winning contractors for any of the 23 packages (update: the Daily FT has since named the winners of all 28 contracts in Monday’s decision; see the updates above), the construction period for either phase, or the expected completion dates. No filing states the funding source — domestic borrowing, foreign financing or Treasury provisions — for the Rs 502.16 billion. (Update: the minister has since claimed the two expressways are wholly tax-funded; see above.)

The EconomyNext account added on 17 November answers none of these. It also does not reconcile its “less than 25 per cent” capital-execution figure against the 27.9 per cent on the same denominator reported earlier, name the Treasury officials it cites, or say how the new 2027 approval and procurement process would differ from the current one.