The Cabinet has approved Stage I of the Oliyamulla pumping station project at an estimated cost of Rs 5,962.13 million. The project aims to cut flood risk in the Mudun Ela catchment, where floodwater from the Kelani River enters urban areas through the canals.
The work will be carried out from 2027 to 2031, Cabinet Spokesman Minister Nalinda Jayatissa said, the Daily FT reported on Wednesday. The proposal came from Transport, Highways and Urban Development Minister Bimal Rathnayake.
The problem it addresses
The Mudun Ela canals join the Kelani River at Oliyamulla, Peliyagoda and Pethiyagoda. When the upper reaches of the river flood, water flows back up the canals into these built-up areas and floods low-lying land. Studies recommended a pumping station at Oliyamulla, where the catchment’s main canal meets the river.
Two stages, 35 cubic metres a second
The project will be financed by the Government of Sri Lanka and the Japan International Cooperation Agency (JICA). Its total pumping capacity will be 35 m³/s:
| Stage | Capacity | Status |
|---|---|---|
| I | 15 m³/s | Approved, Rs 5,962.13 million, 2027–2031 |
| II | 20 m³/s | No cost or timetable reported |
How it connects to the Japanese grant
On 28 October this desk reported that Japan had granted JPY 2.179 billion, about Rs 4.5 billion, for a stormwater pumping station in the Mudun Ela sub-basin covering Wattala and Peliyagoda. That station also has a capacity of 15 cubic metres a second.
The location, the catchment and the capacity all match Stage I. If the Japanese grant is the JICA share, about Rs 1.4 billion of the Rs 5.96 billion would fall to the government. That is this desk’s calculation. The Daily FT report does not say how the cost is split. The Budget 2027 plans for flood control in Colombo’s canal network also covered the Mudun Ela area.
Not reported
The report does not give the date of the Cabinet meeting, the government’s share of the cost, who will build the station, or when Stage II might go ahead. It does not say how many households or how much land the project is expected to protect.
Sourcing note
Single source. The Daily FT was the only verified newsroom on this desk’s rails carrying the decision at the time of writing. The Daily Mirror, NewsFirst and Hiru News had not reported it, and Ada Derana remains blocked (HTTP 403).