CEB lost Rs 38.7 billion last year, Power Minister tells Parliament, blaming tariff swings
Anura Karunatilaka put the CEB's 2025 net loss at Rs 38,739mn and rejected Dayasiri Jayasekera's claims about poor-quality coal and who runs the ministry.
Anura Karunatilaka put the CEB's 2025 net loss at Rs 38,739mn and rejected Dayasiri Jayasekera's claims about poor-quality coal and who runs the ministry.
The former energy minister says 35,209 MWh of hydro used to cover the coal shortfall was assigned no value, understating the loss by about Rs. 2.2 billion.
The Special Presidential Commission says it has reviewed 37 complaints and recorded statements from 72 people since being appointed on April 17.
Trade unions say the National System Operator's report on the 17 October collapse does not address whether substandard coal disabled the Lakvijaya units.
Ranawaka alleges fraudulent coal purchases and foreign connections but has presented no documents or evidence.
MP blames inferior coal for Norochcholai failure and power cuts. Criticizes government elected on 'whole country' campaign slogan.
President Dissanayake has extended the coal procurement inquiry by two months through Gazette No. 2510/81. Its previous term expired on October 16.
The oversight committee chairman put the cost of substandard coal at Rs. 18.3 billion, about Rs. 335 million above the figure he gave Parliament on 8 October.
SLPP MP Chanaka alleges substandard coal caused Norochcholai blackout. Official cause under investigation; long-term damage expected.
The commission has recorded evidence from more than 70 people and expects to finish next week. Its current term ends on October 16.
Anura Karunathilake put the loss at Rs. 15.765 billion and said Rs. 16.989 billion in penalties and performance bonds has been withheld from suppliers.
Those served have until October 9 to respond, with the Presidential Commission of Inquiry due to conclude its term on October 16.
The remanded SLPP MP told Parliament senior Ministers may have been behind the diverted Treasury payment, and questioned the speed of coal shipments.
Coal tender documents used estimates instead of actual plant requirements, audit officer tells Presidential Commission.
Energy Minister says coal procurement for 2026/27 is settled with shipments due in September, while hydropower now meets 48% of electricity demand.
The former state minister alleged bid documents were issued a day after a supplier finished registering, and questioned the rejection of Lakvijaya lab reports.
Lanka Coal Chairman Jayantha Rathnayake told the Presidential Commission the leaked call concerned a performance bond deadline, denying any irregularity.
Former minister Patali Champika Ranawaka has been summoned before the commission investigating coal procurement and related matters during his tenure.
Sri Lanka's coal procurement commission summoned six witnesses and heard that Lakvijaya plant data went undigitised from 2011 to 2016.
Sri Lanka's coal procurement commission held a third day of hearings, summoning three officials including a Lakvijaya plant manager.
The Presidential Commission probing coal imports since 2009 made an on-site inspection at the Norochcholai Lakvijaya Power Plant, the PMD said.
Sri Lanka's coal procurement commission has questioned 40 officials, including procurement committee members, with open hearings set for the first week of.
Samagi-aligned trade union spokesperson Ananda Palitha says LP gas could rise by Rs. 300-500 per cylinder this week and water tariffs by June 15.
55,000 MT of substandard coal from MV JOSCO YONGZHOU were unloaded at Norochcholai by June 2 despite a Bureau Veritas reject ruling, the FLO warned.