Coal ship reaches Puttalam as minister says replacement cargo ends shortage
Coal ship IVS TRADER delivered 60,000 tonnes to Norochcholai, replacing a rejected consignment. Another shipment expected September 12.
Coal ship IVS TRADER delivered 60,000 tonnes to Norochcholai, replacing a rejected consignment. Another shipment expected September 12.
Generation at Norochcholai has been limited as coal stocks fell, but hydropower is covering the gap. Two shipments arrive on 4 and 12 September.
The National System Operator says kites entangled in 220 kV and 132 kV lines destabilised the grid on September 2, cutting supply to some consumers.
Rooftop solar systems above 300 kW must stop generating from 8 a.m. to 3 p.m. daily through Sunday as holiday demand falls, the grid operator says.
Electricity Distribution Lanka will install 300,000 Time-of-Use smart meters over two years, funded from the remainder of a US$15m ADB concessional loan.
Anura Karunatilaka says 160MW of battery storage reaches the grid by December, with tenders out for 250MW more and 150MW of ground-mounted solar.
PUCSL sets new renewable feed-in tariffs from August 25, paying up to Rs. 45.53 a unit for rooftop solar with storage, targeting 450MW by March 2027.
The National System Operator says catchment rainfall has held hydro storage at 67%, while Irrigation Department reservoirs have slipped to 35%.
Energy Minister says coal procurement for 2026/27 is settled with shipments due in September, while hydropower now meets 48% of electricity demand.
Commercial-scale battery systems at 16 transmission substations are nearing completion, storing daytime solar power to cut nighttime diesel generation.
16 km transmission cable project from Kerawalapitiya to Colombo Port begins construction via $52 million AIIB loan.
The regulator says a 0.3% rise in supply costs did not warrant a tariff revision, with a Rs. 26.75 billion surplus from the first quarter carried forward.
The National System Control Centre says there is no observed risk of power cuts in the near term, as the President convenes an energy stability meeting.
Man climbs transmission tower in family dispute, blacks out seven Matara areas for two hours; admits offense.
The National System Operator says it aims to reduce diesel-based electricity generation to 0.5% within two years, saving an estimated Rs. 30 billion.
Samagi-aligned trade union spokesperson Ananda Palitha says LP gas could rise by Rs. 300-500 per cylinder this week and water tariffs by June 15.
IMF Mission Chief Papageorgiou confirmed Sri Lanka has restored cost-reflective fuel and electricity pricing, a precondition for the Board review.
NSO disconnected and then restored supply to ~100 areas after a Vesak-day demand slump and has asked rooftop solar owners to switch off again on Sunday.
Energy Minister Karunathilaka told Parliament no PUCSL tariff revision will be sought before September, with the government absorbing a Rs.15 billion subsidy.
CEB engineers expect a sharp drop in thermal and coal generation costs as Mahaweli and Laxapana reservoirs fill up amid widespread heavy rains.
Energy Minister Karunathilaka says compensation payments to voluntary retirees in the electricity sector will start within days, after a Monday review meeting.
Energy Minister Anura Karunathilaka says Treasury will fund 100% for some successor companies and 50% for NSO and Transmission Network staff.
Anura Karunathilaka says 50% of compensation for ex-CEB retirees will be paid via Treasury funds by May 15, with the remaining 50% to follow shortly after.
President says diesel costs Rs.482/litre to import while sold at Rs.382, with Rs.60bn allocated to subsidies as coal and reservoir levels worsen.